Symposium gates
Gate by gate: what is checked, by whom, and what blocks progress.
Gates in the plan
The plan has five numbered gates (G0-G4), two soft gates at the end of Day 1 and Day 3, and a human criteria check at the start of Day 4. The phases are Prep (Day 0), Problems (Days 1-2), Decide (Days 3-4) and Solutions (Days 5-7). A day does not start until the previous gate line has passed. Every gate result is written as a gate-report object (see Schemas).
human marks a gate that needs a decision from Mathew. Human gates are scheduled at their real duration but run asynchronously.
| Gate | When | What is checked | Who decides | Evidence required | Pass / fail rule |
|---|---|---|---|---|---|
| G0 human | End of Day 0 (S0.1-S0.3); Day 0 | Part 1 (S0.1): all packs under budget and schema examples validate. Part 2 (S0.2): every persona provenance id verified or struck. Dry run (S0.3): dry-run objects schema-valid; calibration file updates the token and wall-clock constants. | schema-gate + Mathew | G0 gate report; pack index; provenance register with status updated; calibration file. | Pass: packs under budget; 100% of provenance ids verified or struck (struck items removed from persona sheets); dry-run objects 100% schema-valid after one retry. |
| G1-soft soft | End of Day 1 (S1.5); Day 1 | Every one of the 15 modality rooms has produced output; expert requests decided at intake. | schema-gate (MC decides expert intake) | G1-soft gate report; Day 1 digest; expert-request decisions. | Pass: all 15 rooms have at least one valid problem statement and a digest. Coverage rule: every pack has at least one position paper by the end of Day 1. |
| G1 human | S2.5, end of Day 2; Day 2 | The problem register (deduped, ranked, frozen). | schema-gate + Mathew | G1 gate report; frozen problem register; expert-request decisions. | Pass: all problem statements valid; unverified ledger fraction at most 10%; zero claims without evidence; no persona claim without a provenance id. Mathew approves the frozen register. |
| G2-soft soft | S3.7, end of Day 3; Day 3 | Draft decision records; which options survive to scoring. | schema-gate | G2-soft gate report; Day 3 digest. | Pass: draft decision records validate. Debate verdicts stay advisory until G2. |
| Criteria human | S4.0, start of Day 4; Day 4 | Decision criteria and their weights. | Mathew (async) | Criteria file with weights. | Pass: weights confirmed or edited by Mathew. |
| G2 human | S4.3, end of Day 4; Day 4 | Ranked decision records with dissent and reversibility. | schema-gate + Mathew | G2 gate report; ranked decisions; decision records with status. | Pass: decision records valid; unverified fraction at most 8%; every accepted decision has at least one solution owner. Mathew accepts, edits or rejects each. No central ADR number is claimed. |
| G3 human | S5.4, end of Day 5 (applies through Day 6); Day 5 | Experiment plans, hardware allocation, safety review and the bench schedule. | schema-gate + Mathew, per hardware step | G3 gate report; bench schedule; experiment plans with approval flag. | Pass: plans valid; offline-first ordering respected; every hardware step individually approved by Mathew. On the Day 6 benches, any deviation aborts the step. |
| G4 human | S7.3, Day 7; Day 7 | The final report and the final ledger after a last red team. | schema-gate + Mathew (sign-off) | G4 gate report; final report; final ledger. | Pass: all objects valid; unverified fraction at most 5%; zero claims without evidence; all persona claims carry provenance ids. |
Sources: the plan's day schedule and schema-validation section, the syllabus "Gates at a glance" table and the session gate lines, and the schemas README.
Each gate
G0 human decision
- When: End of Day 0 (S0.1-S0.3); Day 0.
- Checked: Part 1 (S0.1): all packs under budget and schema examples validate. Part 2 (S0.2): every persona provenance id verified or struck. Dry run (S0.3): dry-run objects schema-valid; calibration file updates the token and wall-clock constants.
- Who decides: schema-gate + Mathew.
- Evidence: G0 gate report; pack index; provenance register with status updated; calibration file.
- Pass / fail: Pass: packs under budget; 100% of provenance ids verified or struck (struck items removed from persona sheets); dry-run objects 100% schema-valid after one retry.
G1-soft soft gate
- When: End of Day 1 (S1.5); Day 1.
- Checked: Every one of the 15 modality rooms has produced output; expert requests decided at intake.
- Who decides: schema-gate (MC decides expert intake).
- Evidence: G1-soft gate report; Day 1 digest; expert-request decisions.
- Pass / fail: Pass: all 15 rooms have at least one valid problem statement and a digest. Coverage rule: every pack has at least one position paper by the end of Day 1.
G1 human decision
- When: S2.5, end of Day 2; Day 2.
- Checked: The problem register (deduped, ranked, frozen).
- Who decides: schema-gate + Mathew.
- Evidence: G1 gate report; frozen problem register; expert-request decisions.
- Pass / fail: Pass: all problem statements valid; unverified ledger fraction at most 10%; zero claims without evidence; no persona claim without a provenance id. Mathew approves the frozen register.
G2-soft soft gate
- When: S3.7, end of Day 3; Day 3.
- Checked: Draft decision records; which options survive to scoring.
- Who decides: schema-gate.
- Evidence: G2-soft gate report; Day 3 digest.
- Pass / fail: Pass: draft decision records validate. Debate verdicts stay advisory until G2.
Criteria human decision
- When: S4.0, start of Day 4; Day 4.
- Checked: Decision criteria and their weights.
- Who decides: Mathew (async).
- Evidence: Criteria file with weights.
- Pass / fail: Pass: weights confirmed or edited by Mathew.
G2 human decision
- When: S4.3, end of Day 4; Day 4.
- Checked: Ranked decision records with dissent and reversibility.
- Who decides: schema-gate + Mathew.
- Evidence: G2 gate report; ranked decisions; decision records with status.
- Pass / fail: Pass: decision records valid; unverified fraction at most 8%; every accepted decision has at least one solution owner. Mathew accepts, edits or rejects each. No central ADR number is claimed.
G3 human decision
- When: S5.4, end of Day 5 (applies through Day 6); Day 5.
- Checked: Experiment plans, hardware allocation, safety review and the bench schedule.
- Who decides: schema-gate + Mathew, per hardware step.
- Evidence: G3 gate report; bench schedule; experiment plans with approval flag.
- Pass / fail: Pass: plans valid; offline-first ordering respected; every hardware step individually approved by Mathew. On the Day 6 benches, any deviation aborts the step.
G4 human decision
- When: S7.3, Day 7; Day 7.
- Checked: The final report and the final ledger after a last red team.
- Who decides: schema-gate + Mathew (sign-off).
- Evidence: G4 gate report; final report; final ledger.
- Pass / fail: Pass: all objects valid; unverified fraction at most 5%; zero claims without evidence; all persona claims carry provenance ids.
Schema validation at the phase gates
All outputs of a phase are validated against their schema (chosen from each object's schema_type) before the next phase starts. Every session in the syllabus and the run of show names its input and output schema types.
- Ledger checks: evidence coverage; unverified fraction at most 10% at G1, 8% at G2, 5% at G4; zero failed entries; zero persona claims without provenance ids.
- Bounce once, then block: a failing object goes back to its author once with the validator error. A second failure blocks the gate and goes to the MC.
- No claim without evidence: every claim has at least one evidence reference, which must resolve to a ledger id, a context-pack anchor or a repository path.
- Persona claims: a claim is either persona-grounded (must cite a provenance entry) or persona-stylized (allowed for analogy and voice only, never usable as decision evidence).
- Failed entries: any ledger entry marked failed blocks the gate until it is struck or fixed.
- Coverage: every one of the 15 packs must have at least one position paper by the end of Day 1.
- Hardware: a bench-hardware experiment plan needs a required human approval and a named approver before its status can leave
planned. - Topic ids must come from the plan's topic registry, or use the on-demand
X-*prefix. - Gate report contents: artifacts checked (each with schema, valid flag and errors), ledger checks, per-pack coverage, thresholds, result (pass, fail, or pass with waivers), waivers, and human sign-off.